Technology Initiatives

Re-engineering for a Sustainable Future

Internet & WiFi Network Upgrade

Juniper Networks will run all campus wired and wireless networks by August 2023. 

Internet & WiFi Network Upgrade

Juniper Networks will run all campus wired and wireless networks by August 2023.

What is it?

The wired and wireless networks that provide internet access to the campus will be consolidated onto Juniper Networks.

Why are we doing it?

The majority of the hardware that provides wired and wireless network service was end-of-life and unable to support current network standards such as WiFi 6. By upgrading this service, UNCG will enjoy improved wireless connectivity, enhanced network capabilities, a better mobile user experience, WiFi 6 support, and support for home devices in student housing.

How will I be impacted?

The upgrades will occur at night and on weekends. Subscribe to ITS News for updates and announcements on when downtimes will occur. 

When will this be implemented?

Between January and August 2023, wired and wireless services will be upgraded. Check your building’s status below:

BuildingStatusDate
101 S. ElmComplete5/30/23
1100 West MarketComplete6/6/23
119 Mciver StreetComplete5/9/23
127 Mciver StreetComplete4/27/23
1510 WalkerComplete4/17/23
1605 Spring GardenComplete7/25/23
326 TateComplete5/15/23
328 TateComplete7/25/23
536 Highland AveCompleteSummer 2023
723 KenilworthComplete5/22/23
821 AycockComplete5/22/23
840 Neil StComplete6/1/23
842 Gate CityCompleteSummer 2023
903 W. Gate CityCompleteSummer 2023
996 Spring GardenComplete5/15/23
Admissions Visitors CtrComplete5/22/23
Alumni HouseComplete4/17/23
Bailey HallComplete7/21/23
Baseball StadiumCompleteSummer 2023
Baseball Stadium Lot 9CompleteSummer 2023
Becher WeaverComplete6/14/23
Brown BldgComplete6/8/23
Bryan BldgComplete4/4/23
Campus MinistriesComplete6/14/23
Campus PoliceComplete5/23/23
Campus SupplyComplete6/14/23
CarmichaelComplete7/25/23
Carter ChildcareCompleteSummer 2023
Chemical SafetyComplete7/25/23
Coit HallComplete3/13/23
Cone BldgComplete5/15/23
Cone HallComplete7/12/23 Daytime
CurryComplete5/18/23
Dining HallComplete6/7/23
EberhartComplete5/17/23
EUCComplete5/18/23
Faculty CenterCompleteSummer 2023
FergusonComplete4/19/23
ForneyComplete5/24/23
FoustComplete6/14/23
Gove HealthComplete6/7/23
GrahamComplete6/14/23
Graphics and PrintingComplete7/25/23
Gray HallComplete7/21/23
Gray HomeCompleteSummer 2023
GroganComplete7/12/23 Daytime
Guilford HallComplete7/18/23 Evening
HaywoodComplete7/12/23 Morning
HHP/ColemanComplete4/18/23
HighlandComplete7/19/23 Morning
HinshawComplete7/21/23
Humanities and ResearchComplete3/13/23
Jackson LibraryComplete5/25/23
JamisonComplete7/21/23
JeffersonComplete7/20/23 Daytime
JSNNComplete3/13/23
Kaplan SRCComplete5/23/23
LeeComplete7/17/23 Evening
LexingtonComplete7/13/23 Daytime
Lofts on LeeComplete7/12/23 Morning
Mary FoustComplete7/18/23 Evening
McCormickComplete7/13/23 Daytime
Mciver Parking DeckComplete5/30/23
McnuttComplete3/13/23
Moore BldgComplete5/31/23
Moore Nursing AnnexComplete5/15/23
Moore-StrongComplete7/11/23 Evening
MossmanComplete4/19/23
MusicComplete6/6/23
New Nursing BldgComplete5/16/23
North Campus DixonComplete6/5/23
North Campus MehlComplete6/5/23
North Drive Child CareCompleteSummer 2023
Oakland DeckCompleteSummer 2023
Oakland WarehouseComplete5/30/23
PettyComplete5/31/23
Phillips HawkinsComplete7/18/23 Evening
Power SubstationComplete4/17/23
Ragsdale-MendenhallComplete7/10/23 Evening
Rec FieldCompleteSummer 2023
ReynoldsComplete7/23/23 Daytime
School of EdComplete6/1/23
Shaw BldgComplete7/11/23 Evening
Sink BuildingComplete4/3/23
Sink GarageComplete4/3/23
Soccer FieldComplete7/25/23
Softball StadiumComplete7/25/23
South Chiller PlantComplete4/3/23
SpencerComplete7/18/23 Evening
Spring GardenComplete7/17/23 Evening
Steam PlantComplete7/25/23
Stone BldgComplete5/24/23
Studio Art BldgComplete6/14/23
Sullivan ScienceComplete6/8/23
Taylor TheaterComplete6/8/23
Tower VillageComplete7/20/23 Daytime
Turf MaintenanceCompleteSummer 2023
UNCG AuditoriumComplete6/14/23
Union HallComplete7/19/23 Daytime
University Relations/500 Forest StComplete7/25/23
Walker DeckComplete4/17/23
Weil-WinfieldComplete7/11/23 Evening

What do I need to do?

Nothing. This upgrade is completely behind the scenes.

Major Milestones

Winter Break 2022

Completion of new wireless hardware deployment

Winter Break 2022
Summer 2023

Completion of new wired hardware deployment

Summer 2023

Stay Up-To-Date

Subscribe to ITS News.


SEND US YOUR QUESTIONS

Help us make the FAQs better, more informative.